Weekly Report 17/06/2012-24/06/2012

Tasks:
+Preparation of Uhx1 boards
+Pcb designs for Uhx1 and Bim2A boards
+Testing of soundmodem with Bim2A and Uhx1 boards

Completed:
+Uhx1 boards are prepared and tested successfully.

Continuing:
+Pcb designs are ongoing due to the many changes while prototyping the Uhx1 boards.

Delayed:
+Testing of soundmodem is delayed due to complications while preparing and testing Uhx1 boards.

Canceled:
+none

Next Week:
+Prepare the list of experiments to be performed.
+Do the experiments.

Notes:
+none